Why would a project manager benefit from distinguishing between primary tasks and dependent tasks? O A. This would enable the manager to avoid scope creep. B. This would enable the manager to draft a dependency schedule. • C. This would enable the manager to build a budget. O D. This would enable the manager to determine how many people he or she needs on the project.

Other

Question
Why would a project manager benefit from distinguishing between primary
tasks and dependent tasks?
O A. This would enable the manager to avoid scope creep.
B. This would enable the manager to draft a dependency schedule.
• C. This would enable the manager to build a budget.
O D. This would enable the manager to determine how many people he
or she needs on the project.
Answer

B. This would enable the manager to draft a dependency schedule.

Download to view full explanation
Distinguishing between primary tasks and dependent tasks is important for a project manager because it helps in drafting a dependency schedule. A dependency schedule is a...